Another day of lovely progress…

Our first shipment of servers arrived in a big truck.  Thank heavens for the lift.
The second ducting has started going in on the other side of the road and runs half the length, hopefully that section will be done in another day’s work.
The plasterers have been busy, and the new walls around the UPS room have been plastered on both sides and are looking good.
The power sockets have started being run, and I’m glad I don’t have to make sense of that collection of wires.

Off camera, cable trays running power above the suspended ceiling have been going in (loudly) and cabling has started for the office.

Hopefully come the end of Monday we can bring you pictures of the office framework going up.  Fingers crossed.

And now, the pictures.

No comments for this entry yet...

Leave a Reply

Looking for something?

Use the form below to search the site:

Still not finding what you're looking for? Drop a comment on a post or contact us so we can take care of it!

Visit our friends!

A few highly recommended friends...