Progress 27th Jan
by Mat Buckle on Jan.27, 2009, under Build Progress
Progress today looks good. We picked up a change which needed to be made with the layout of the overhead racks which hopefully does not cause to much of a delay. Partitioning for the upstairs offices has begun with the big task of getting all the material upstairs. Jon also made further progress with testing the Cisco Routers.
- Jon testing Cisco Routers
- The Cisco Router
- Temp Plastic dividing the Upstairs Office allowing a clean working area
- Upstairs just before partitioning begins
- Plaster Board for partitioning
- The start of a ramp into the server room which will store against the wall
- starting to to look better
- The air con in the UPS room
- Power
- Big Cables
- Overhead racks
- Power Sockets
- Power cables running to the generator
- Still more plaster board which needs to be moved upstairs
- Fetching sand
- Preparing for the concrete slab
- Concrete slab will be put in tomorrow as a base for the generator
- Extended space for the aircons
- One of the fibres coming into the DC
- The Aircon for the UPS room
- Our street name
- A bit of advertising
- Sand for the concrete slab
- Measuring up for the burglar guards
- Ready for the pull through of fibre towards the DC
- The Cisco Router