Progress 28th Jan
by Mat Buckle on Jan.28, 2009, under Build Progress
Sorry for the bad quality of the pictures. We were not meant to be at the DC today but through circumstances ended up there any way and had the opportunity to take pics. Because of this they are taken with the phone cam and therefore not good quality.
The Window film decision was made for blackout vinyl and opaque white on upper rear of the building. This allows us to get a good combination of security, sun light and good looks. We also had the delivery of the 4.5 km Optic Fibre which will be pulled through over the next few days. The Paxman final decision was also reached so that our key areas are controlled electronically by card. The UPS system and batteries arrived also whilst we were there.
- Steel rienforcing for the concrete pad
- UPS
- The UPS units
- Putting in the frame work for the partitioning
- Cutting for the overhead containment
- Tar
- Batteries for the UPS (5 pallets)
- Loading Tar for the external air con units
- leveling the tar
- Compacting
- The Black vinyl at bottom with white film at top
- Black Vinyl for Security
- The skeleton of the board and break rooms
- Partitioning
- The tracks for the partitioning on the floor
- Box for connection of our fibre to the ring