Progress 31st
by jon on Jan.31, 2009, under Build Progress
UPS’s are now being cabled up
Partitioining is progressing well with the passage taking shape
Box build for South-bound route has started.
More testing for the power distribution.
- UPS
- Start of cabling to the UPS’s
- Cable containment for the UPS room
- Cables for the UPS’s (will be on copex for protection)
- North route fiber is now in the building
- Testing begin’s on the power distrobution
- Gen Set cables
- Testing on PDU
- Partitioning
- Partitioning
- Concrete pad now curing
- New path
- New south bound box being built
- South bound box
- South Bound box
- Southbound box