Archive for February, 2009
Network complete
by chrisbyrd on Feb.24, 2009, under Build Progress
The final leg of our fibre network was completed yesterday evening. The 20Gbps network is now live and running with full diversity and protection all the way back to London and out to the Internet.
The air-conditioning install is continuing, but was pushed a day or so behind schedule
No photos today unfortunately – expect more shortly…
Progress 21th Feb
by chrisbyrd on Feb.21, 2009, under Build Progress
Everything is progressing very well. The fist of our office furniture has arrived, including a rather large solid oak reception desk. Installation of the Paxton proximity door security system is nearly complete and the two main fire suppression and detection systems are now up and running.
Installation of the air-conditioning systems has been progressing well this week, and is scheduled to be finished by Wednesday next week. Final fibre pulling and splicing was completed at 5am this morning (due to traffic control restrictions) and we’re hoping to bring this 10G link into live service on Monday
See below for photos of this week’s progress
Power-up! (Friday 13th!)
by chrisbyrd on Feb.14, 2009, under Build Progress
Friday was a very successful day. The UPS cluster and first generator have been commissioned, fully tested and also undergone several hours of load-bank testing. A number of different ‘real’ mains-failure scenarios were tested and the power backup systems performed flawlessly (without a single ‘tweak’ required!). The entire electrical infrastructure is now fully operational.
The cold-aisle containment is also now complete on the first pod (ie two contained rows) of racks.
There is more fibre pulling scheduled for Monday and Tuesday, with final splicing & testing on Wednesday. The final 10G network link will then be operational towards the end of the week. Thursday will see the main downflow air conditioning equipment installed and commissioned.
We’re very much on target for full completion by the end of the week
Photos from Friday below…
Progress 12 Feb 09
by Daniel B on Feb.12, 2009, under Build Progress
The main board is up and running, the generator is cabled and due to be commisioned tomorrow.
The plaster upstairs is drying nicely and should be painted early next next week.
- The PDU’s being finished yesterday
- Some of the plastering being done upstairs
- Some of the plastering being done upstairs
- More electrics
- Pretty lights on the main board
- PDU output readings
- Incoming power readings
- The generator wired up
- The generator wired up
- The data floor looking good
- Don’t the racks look pretty
- What a lot of battery boxes
Progress 11th Feb 09
by jon on Feb.11, 2009, under Build Progress
The DC build is progressing well with the main panel now 90% installed (to be completed tomorrow), UPS cabling done, the first pod of racks has been installed and work has started on the containment for the cables to the generator (to be completed tomorrow).
Tomorrow United Utilities will arrive to upgrade part of our power supply, the UPS battery build starts and the generator cabling starts!
We hope to have initial power to the rack by Monday and Air conditioning around 1 week later.
The office has started to be plastered!
We will start the job of installing around 200 cables into patch panels late Friday/Monday.
- UPS room Cabling
- UPS room Cabling
- UPS room Cabling
- UPS room Cabling
- UPS room Cabling
Progress 10 Feb 09
by Daniel B on Feb.10, 2009, under Build Progress
More progress has been made on the little details, including the lines of racks shaping up nicely and last of the plaster boarding is going up upstairs.
The most important change today is this one though. The main board is in place!
- Main board in position
- Close up of the board
Progress 09 Feb 09
by Daniel B on Feb.10, 2009, under Build Progress
Not much chatter tonight, just some pictures
- Partitioning
- Walls to go up
- Walls to go up
- Partioning
- Almost done
- Partitioning
- Lighting being redivided
- Partitions coming along
- Our kitchen is almost done
- Our kitchen is almost done
- Preparing for the big panel
- Earthing
- A row of racks
- A row of racks
- Working on the security systems
- Working on the earthing
- Drilling a hole
- Drilling a hole
- Drilling a hole
- Corridor
Progress 7th Feb – Network is up!
by chrisbyrd on Feb.07, 2009, under Build Progress
The first dark-fibre network link is now operational. This link is actually the 27km 10Gig backup route, linking the datacentre to one of our two main Manchester Points-of-Precense (POPs) located at one of the Telecity facilities on the Science Park. The primary network link will be a shorter 9km dark-fibre route and is anticipated to be online within the next week or so (weather permitting!).
We had hoped to also bring this second network route online this weekend, but the final duct construction ‘en route’ had been delayed due to the recent adverse weather conditions. These duct and box builds are are now progressing well (see photos below) and are due to be completed within the next 48 hours. The final 2km of fibre pulling is scheduled for later this week – again, weather permitting!
Progress 05 Feb 09
by Daniel B on Feb.05, 2009, under Build Progress
A short update and some pictures…
Progress is continuing with wiring the power system.
The fire suppression system is progressing nicely.
The first of our external cameras is up and running.
- Top PDUs
- Bottom PDUs
- Fire suppression system
- Fire suppression system
- Generator fuel tank
- Camera housing
- Awesome camera
Progress 4th February
by tomh on Feb.04, 2009, under Build Progress
Today we have had some very significant deliveries to the datacentre. We have had the generator delivered at the exact same time we had gas cylinders delivered and a bit later on, half of our racks were delivered. We have had a lot of progess with our fibre connectivity, we should have that live very shortly. We have had people splicing today with the fibre. We also had the office people in today who continued their work on the development of the office partitions upstairs, they haven’t been able to access the site recently due to weather restrictions. Today, we had one of our newly delivered network cameras configured which you can see below along with plenty of other pictures from todays events.
- First signs of the generator
- Gas cylinders
- Generator entering the site
- Generator
- Generator becomes airborne with crane
- Lining the generator up
- Generator in position
- Gas cylinder
- Racks being delivered
- Workers moving the racks into the datacenter
- Switch, Network Camera and an Wireless Access Point
- Racks in the DC
- Close up on three racks
- Splicing fibre
Progress 3rd Feb
by Mat Buckle on Feb.04, 2009, under Build Progress
Today we had one of the major step forwards in intruder protection with the start of the installation of the windows bars. As you can see they are pretty well re-inforced. We have had a lot of electricians in working with the switch board and the power distribution unit. They’re currently glanding from the main board around the datacenter. We had an arrival of our wireless access points, we were the last delivery of the day! More deliverys today, quite importantly the generator will be arriving, the picture below shows the spot waiting for it.
- All those plants went into Dave’s Mercedes!!
- A squeeze
- Fire alarm
- cables coming from switch board into UPS room
- Burglar guards and the UPS
- Burglar Bars
- Fire Alarm
- Power
- Cables from Generator
- Fire Protection
- Connecting up
- Power Sockets
- Cables from Generator
- The over head racks finished
- Concrete Prepared for the generator
Progress 2nd Feb
by jon on Feb.02, 2009, under Build Progress
Cable testing is continuing. The cables between the power distro boxes and main panel have been installed and the cabling between the main panel and UPSs has also been installed. Fire suppression install is going well.
- Fire supression system cabling
- UPS install
- Main PDU distro cables
- Main Panel cabling
- Panels for the fire supression
Update
by Mat Buckle on Feb.02, 2009, under Build Progress
- The Black Vinyl from the Outside
- UPS units
- testing power sockets
- padding on hand rails
- Dave & Jean
- Fibre
- Burglar guards for UPS room before Powder coating (2, one behind the other)

















































































































































