Progress 3rd Feb

by Mat Buckle on Feb.04, 2009, under Build Progress

Today we had one of the major step forwards in intruder protection with the start of the installation of the windows bars. As you can see they are pretty well re-inforced. We have had a lot of electricians in working with the switch board and the power distribution unit. They’re currently glanding from the main board around the datacenter. We had an arrival of our wireless access points, we were the last delivery of the day! More deliverys today, quite importantly the generator will be arriving, the picture below shows the spot waiting for it.

:, , , ,