Progress 11th Feb 09
by jon on Feb.11, 2009, under Build Progress
The DC build is progressing well with the main panel now 90% installed (to be completed tomorrow), UPS cabling done, the first pod of racks has been installed and work has started on the containment for the cables to the generator (to be completed tomorrow).
Tomorrow United Utilities will arrive to upgrade part of our power supply, the UPS battery build starts and the generator cabling starts!
We hope to have initial power to the rack by Monday and Air conditioning around 1 week later.
The office has started to be plastered!
We will start the job of installing around 200 cables into patch panels late Friday/Monday.