M247 Ltd Manchester Datacentre Build Blog

Power-up! (Friday 13th!)

by chrisbyrd on Feb.14, 2009, under Build Progress

Friday was a very successful day. The UPS cluster and first generator have been commissioned, fully tested and also undergone several hours of load-bank testing. A number of different ‘real’ mains-failure scenarios were tested and the power backup systems performed flawlessly (without a single ‘tweak’ required!). The entire electrical infrastructure is now fully operational.

The cold-aisle containment is also now complete on the first pod (ie two contained rows) of racks.

There is more fibre pulling scheduled for Monday and Tuesday, with final splicing & testing on Wednesday. The final 10G network link will then be operational towards the end of the week. Thursday will see the main downflow air conditioning equipment installed and commissioned.

We’re very much on target for full completion by the end of the week :-)

Photos from Friday below…

1 comment for this entry:
  1. Adam

    mmmm…. Geek fodder!

Leave a Reply

Looking for something?

Use the form below to search the site:

Still not finding what you're looking for? Drop a comment on a post or contact us so we can take care of it!

Visit our friends!

A few highly recommended friends...