March 8th Update – we’re online!

by chrisbyrd on Mar.08, 2009, under Build Progress

Apart from a final ’snag list’ of cosmetic touch-ups, the datacentre is now complete :-)

  • The fully resilient network is now operational
  • The N+1 close-control cooling is up and running
  • Local Authority Building Control have signed off all the works
  • Electrical infrastructure is fully complete, certified and online, including generator and N+1 UPS protection and power conditioning
  • The numerous fire detection and suppression systems are now active
  • Security systems are online, including detailed internal & external IP CCTV, proximity door access and priority-response RedCare alarm system

There are now more than 200 live operational servers online at the facility, with another 300 due to be moved over the coming weeks.

The finishing touches are being completed to the office areas, with a view to our permanent sales, technical support and NOC operations moving here within the next couple of weeks.

See below for some photographs of progress over the past week or so…

1 comment for this entry:
  1. Josh Maxwell

    Thanks for posting the article, was certainly a great read!

Leave a Reply

Looking for something?

Use the form below to search the site:

Still not finding what you're looking for? Drop a comment on a post or contact us so we can take care of it!

Visit our friends!

A few highly recommended friends...