Archive for April, 2009
3 April 2009
by Mat Buckle on Apr.03, 2009, under Build Progress
With the ‘move’ from London now finished everything is up and running. The datacentre is in the finishing stages with jobs such sorting and furnishing taking place. With the racks flat packed and brought from London we can also begin the process of building our 2nd pod which should be under demand shortly.
- Sudlows finishing up
- Building racks
- Our 1st Pod
- Top Panels before
- 2nd Pod in progress
- Downstairs phone with siren
- In our 2nd Pod
- Between Pods
- Phil at work
- cables in over head trays
- Top Panels with our own modified cable management
- Floors tiles ready for Drilling and inserting grommits. This will be for the power cables.
- The Doors going on for 2nd pod
- Bare rack flat packed
- Shelving in our store ready for sorting