Archive for December, 2011
Building work started
by Phil Evans on Dec.22, 2011, under DC2 build
Building work has started on phase 1 of our second datacentre build-out. Phase 1 involves the removal of the staircase and the building of a new floor in one of the buildings which will give extra room for our UPS’s.
This is the first 3 days of progress.
- Skip soon to be filled to the brim with concrete
- Safety first
- Carpet removed from the stairs ready for demolition
- The downstairs toilets are slightly out of order
- I swear there used to be a wall there….
- …no matter how much you’re tempted.
- Another wall gone