by jon on Mar.24, 2010, under Facility Information

Our 1u colocation package has recently been updated to include 0.8amps of power as standard, this allows you to run almost any single CPU server!

Leave a Comment more...

Progress 11th Feb 09

by jon on Feb.11, 2009, under Build Progress

The DC build is progressing well with the main panel now 90% installed (to be completed tomorrow), UPS cabling done, the first pod of racks has been installed and work has started on the containment for the cables to the generator (to be completed tomorrow).

Tomorrow United Utilities will arrive to upgrade part of our power supply, the UPS battery build starts and the generator cabling starts!

We hope to have initial power to the rack by Monday and Air conditioning around 1 week later.

The office has started to be plastered!

We will start the job of installing around 200 cables into patch panels late Friday/Monday.

Leave a Comment more...

Progress 2nd Feb

by jon on Feb.02, 2009, under Build Progress

Cable testing is continuing. The cables between the power distro boxes and main panel have been installed and the cabling between the main panel and UPSs has also been installed. Fire suppression install is going well.

Leave a Comment more...

Progress 31st

by jon on Jan.31, 2009, under Build Progress

UPS’s are now being cabled up

Partitioining is progressing well with the passage taking shape

Box build for South-bound route has started.

More testing for the power distribution.

Leave a Comment more...

Progress 29th

by jon on Jan.31, 2009, under Build Progress

The contrete has arrived for the Gen set pad and is being layed now.

Cable tray Version 3 is now being installed

The partitions upstair’s are going up fast.

Fire supression install has started.

Leave a Comment more...

Progress 26th Jan

by jon on Jan.26, 2009, under Build Progress

Work continues at a fast pace with the PDU breaker panels almost done (4/5 done). A 185mm armoured power cable has been hung between the input feed and the main panel (not yet installed), air con installation in the UPS room has started.

Tomorrow the concrete for the generator pad should arrive and the office build out should start.

Leave a Comment more...

Progress 8th Jan

by jon on Jan.08, 2009, under Build Progress

Work has started on stripping out the existing office-grade raised floor in order to install the heavy duty datacentre floor, with 400mm void to allow sufficient air flow for cooling

Leave a Comment more...

Looking for something?

Use the form below to search the site:

Still not finding what you're looking for? Drop a comment on a post or contact us so we can take care of it!

Visit our friends!

A few highly recommended friends...