M247 Ltd Manchester Datacentre Build Blog

Tag: UPS

27th May – Photos of our Colocation Facilities

by chrisbyrd on May.27, 2009, under Facility Information

As part of their case study, our UPS manufacturer sent a photographer to take some pictures of our completed datacentre. See below for the results :-)

Leave a Comment :, , , , , more...

Progress 3rd Feb

by Mat Buckle on Feb.04, 2009, under Build Progress

Today we had one of the major step forwards in intruder protection with the start of the installation of the windows bars. As you can see they are pretty well re-inforced. We have had a lot of electricians in working with the switch board and the power distribution unit. They’re currently glanding from the main board around the datacenter. We had an arrival of our wireless access points, we were the last delivery of the day! More deliverys today, quite importantly the generator will be arriving, the picture below shows the spot waiting for it.

Leave a Comment :, , , , more...

Looking for something?

Use the form below to search the site:

Still not finding what you're looking for? Drop a comment on a post or contact us so we can take care of it!

Visit our friends!

A few highly recommended friends...